Tore Group 2 (0-2)
Activity Predecessor Time
A-7
B - 10
CAS
DB 10
E CD9
FB 10
G F10
2. Using the information from your group, answer the following questions:
a. How many paths are there from the beginning of the network model to the end? (value: 20 points)
b. List the parts of each path. For example, if one path from the beginning to the end is A---Csay "ABC." (value: 20 points)
c. How long is each path? For example, if path ABC is 6. 7. and 9. say "22" because this is the sum of these paths (6+7-9-22). (value: 25 points)
d. Which is the critical path? Remember, the critical path is the longest path. If two paths are equally long (say, you have two paths that are both 30 in length). name both paths. (value 35 points)

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 17:00
Tom had a total of $220 and he spent $35 on a basketball ticket . what percent of his money did he have left?
Answers: 1
question
Mathematics, 21.06.2019 17:30
Two customers went to a post office. first customer paid $12 for 14 and 5 envelopes the second paid 24.80 for 10 postcards and 15 envelopes. what is cost of each envelope?
Answers: 1
question
Mathematics, 21.06.2019 21:30
Plz hurry evaluate the expression a+b where a=8 and b=19
Answers: 1
question
Mathematics, 22.06.2019 00:10
Which polygon is she in the process of constructing ?
Answers: 1
You know the right answer?
Tore Group 2 (0-2)
Activity Predecessor Time
A-7
B - 10
CAS
DB 10
Questions
question
English, 30.07.2019 19:00
question
History, 30.07.2019 19:00
question
Social Studies, 30.07.2019 19:00
question
Biology, 30.07.2019 19:00
question
Biology, 30.07.2019 19:00