Task: Engineers are digging a 3200-foot-long tunnel at a constant rate. After 5 months, the engineers still need to dig 1700 feet to finish the project. How much time does it take to complete the tunnel from start to finish?

Will the engineers have enough time if the project was started in December 2020 and the deadline to finish the project was in August 2021? Please explain your answer for yes or no.

Hint:
y=mx+b (slope-intercept form)
x=time
y=distance
b=3200
Start & Finish: ??
Total length=3200ft

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 14:30
In trapezoid bath, ah=19.7 and et=16.1. identify be.
Answers: 1
question
Mathematics, 21.06.2019 22:10
What is the circumference of a circle with an area of 50.24 cm²?
Answers: 2
question
Mathematics, 21.06.2019 22:40
Present age of man is 45 years, 5 years back his age was 4 times age of his son what is present age of his son?
Answers: 2
question
Mathematics, 21.06.2019 23:00
Events a and b are independent. the probability of a occurring is 2/5. the probability of b occurring is 1/4. what is p(a and b)?
Answers: 2
You know the right answer?
Task: Engineers are digging a 3200-foot-long tunnel at a constant rate. After 5 months, the enginee...
Questions
question
Mathematics, 08.01.2021 21:30
question
Mathematics, 08.01.2021 21:30
question
Mathematics, 08.01.2021 21:30
question
Mathematics, 08.01.2021 21:30
question
Mathematics, 08.01.2021 21:30