subject
Mathematics, 21.07.2020 19:01 stalley1521

35 workers are employed to complete the construction in 16 days. Before the work starts, he is told to complete the task in 14 days. Assuming that all the workers work at the same rate, how many more workers does he need to employ in order to complete the project.

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 17:00
Describe what moves you could use to create the transformation of the original image shown at right
Answers: 1
question
Mathematics, 21.06.2019 18:00
Jack has a piece of red ribbon that is two times as long as his piece of blue ribbon. he says that he can use two different equation to find out how long his piece of red ribbon is compared to his piece of blue ribbon is. is he correct? explain his reasoning
Answers: 1
question
Mathematics, 21.06.2019 21:00
George is putting trim around his rectangular deck, including the gate. he will need 44 feet of trim to do the entire deck. if the deck is 13 feet long, how wide is the deck?
Answers: 2
question
Mathematics, 21.06.2019 22:00
Find the maximum value of p= 4x + 5y subject to the following constraints :
Answers: 3
You know the right answer?
35 workers are employed to complete the construction in 16 days. Before the work starts, he is told...
Questions
question
History, 03.03.2021 05:30
question
Chemistry, 03.03.2021 05:30
question
Physics, 03.03.2021 05:30
question
English, 03.03.2021 05:30