An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total time for all tasks is 18 minutes. The line will operate for 450 minutes per day. Show all relevant calculations. a. What are the minimum and maximum cycle times? b. What range of output is theoretically possible for the line? c. What is the minimum number of workstations needed if the maximum output rate is to be sought? d. What cycle time will provide an output rate of 125 units per day? e. What output potential will result if the cycle time is (1) 9 minutes? (2) 15 minutes?

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 16:00
Use set builder notation to represent the following set: { -3, -2, -1, 0}
Answers: 1
question
Mathematics, 21.06.2019 17:30
Write the following as a base and exponent
Answers: 2
question
Mathematics, 21.06.2019 17:30
What term makes it inconsistent y=2x - 4 ?
Answers: 3
question
Mathematics, 21.06.2019 19:00
What are the solutions of the equation? 6x^2 + 11x + 4 = 0 a. 4/3, 1/2 b. -4/3, -1/2 c. 4/3, -1/2 d. -4/3, 1/2
Answers: 2
You know the right answer?
An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total tim...