An agile team used planning poker to estimate user stories. After all team members read a user story, the facilitator asks everyone to choose a card with estimated number of ideal days to complete a user story and then reveal the card. If estimates were widely different, the facilitator would immediately ask for re-estimates until all the estimates converge. What did the facilitator do wrong? A. Participants used ideal days as the unit for the estimates.
B. Participants re-estimated immediately after everyone revealed their cards.
C. Cards were revealed when the process should have been anonymous.
D. The facilitator did nothing wrong and played by the rules.

ansver
Answers: 2

Another question on Computers and Technology

question
Computers and Technology, 23.06.2019 12:40
According to the video what are some tasks petroleum engineers perform check all that apply
Answers: 2
question
Computers and Technology, 24.06.2019 03:30
Auniform resource locator (url) is a formatted string of text that web browsers, email applications, and other software programs use to identify a particular resource on the internet. true false
Answers: 2
question
Computers and Technology, 24.06.2019 18:30
In what way is your social media footprint related to your digital id
Answers: 1
question
Computers and Technology, 25.06.2019 00:30
Which type of cell references are locked and not automatically updated when it’s copied a)formula b)relative c)absolute d)worksheet
Answers: 1
You know the right answer?
An agile team used planning poker to estimate user stories. After all team members read a user story...
Questions
question
English, 13.12.2020 14:00
question
Mathematics, 13.12.2020 14:00
question
English, 13.12.2020 14:00
question
Chemistry, 13.12.2020 14:00