An agile team used planning poker to estimate user stories. After all team members read a user story, the facilitator asks everyone to choose a card with estimated number of ideal days to complete a user story and then reveal the card. If estimates were widely different, the facilitator would immediately ask for re-estimates until all the estimates converge. What did the facilitator do wrong?
A. Participants used ideal days as the unit for the estimates.
B. Participants re-estimated immediately after everyone revealed their cards.
C. Cards were revealed when the process should have been anonymous.
D. The facilitator did nothing wrong and played by the rules.
Answers: 2
Computers and Technology, 23.06.2019 12:40
According to the video what are some tasks petroleum engineers perform check all that apply
Answers: 2
Computers and Technology, 24.06.2019 03:30
Auniform resource locator (url) is a formatted string of text that web browsers, email applications, and other software programs use to identify a particular resource on the internet. true false
Answers: 2
Computers and Technology, 24.06.2019 18:30
In what way is your social media footprint related to your digital id
Answers: 1
Computers and Technology, 25.06.2019 00:30
Which type of cell references are locked and not automatically updated when it’s copied a)formula b)relative c)absolute d)worksheet
Answers: 1
An agile team used planning poker to estimate user stories. After all team members read a user story...
English, 13.12.2020 14:00
Mathematics, 13.12.2020 14:00
Mathematics, 13.12.2020 14:00
Mathematics, 13.12.2020 14:00
English, 13.12.2020 14:00
Mathematics, 13.12.2020 14:00
Mathematics, 13.12.2020 14:00
Mathematics, 13.12.2020 14:00
Chemistry, 13.12.2020 14:00
Mathematics, 13.12.2020 14:00
Computers and Technology, 13.12.2020 14:00
Physics, 13.12.2020 14:00
English, 13.12.2020 14:00