On April 1st, Mark the Builder entered into a contract of one-month duration to build a barn for Nick. Mark is guaranteed to receive a base fee of $4300 for his services in addition to a bonus depending on when the project is completed. Nick created incentives for Mark to finish the barn as soon as he can without jeopardizing the structural integrity of the barn. Nickn offered to pay an additional 25% of the base fee if the project finished 2 weeks early and 15% if the project finished a week early. The probability of finishing 2 weeks early is 20% and the probability of finishing a week early is 60%.

a) What is the expected transaction price with variable consideration estimated as the expected value?

b) What is the expected transaction price with variable consideration as the most likely amount?

ansver
Answers: 3

Another question on Business

question
Business, 22.06.2019 10:30
Which maxim is being neglected in the following conversation? eli: how did you do at the track meet? caleb: i came in second place! eli: congratulations! what was your time? caleb: six minutes, four seconds. the guy who won only beat me by three seconds. eli: really? katie said the winning time was under 6 minutes. caleb: oh, well, he might have beat me by five seconds. a)maxim of quantity b)maxim of quality c)maxim of relevance d)maxim of manner
Answers: 1
question
Business, 22.06.2019 12:30
Provide an example of open-ended credit account that caroline has. caroline blue's credit report worksheet.
Answers: 1
question
Business, 22.06.2019 19:30
Which of the following constitute the types of unemployment occurring at the natural rate of unemployment? a. frictional and cyclical unemployment.b. structural and frictional unemployment.c. cyclical and structural unemployment.d. frictional, structural, and cyclical unemployment.
Answers: 2
question
Business, 23.06.2019 01:00
Why does the downward-sloping production possibilities curve imply that factors of production are scarce?
Answers: 1
You know the right answer?
On April 1st, Mark the Builder entered into a contract of one-month duration to build a barn for Nic...
Questions