subject
Social Studies, 14.05.2021 16:50 ymlantigua21

Based on the information in the passage, what is the most likely reason the Grand Coulee Dam took longer to complete than the Hoover Dam? 1. Construction of the Grand Coulee Dam began two years after the building of the Hoover Dam started.

2. Construction on the Hoover Dam resulted in a shortage of workers and concrete needed to build the Grand Coulee Dam.

3. Completing the Hoover Dam was a higher priority than the Grand Coulee Dam because farmers and ranchers were depending on it.

04. The greater size and length of the Grand Coulee Dam presented unique challenges that the builders of the Hoover Dam did not face.​

ansver
Answers: 3

Another question on Social Studies

question
Social Studies, 22.06.2019 20:40
The cause and events that led to civil rights
Answers: 1
question
Social Studies, 23.06.2019 04:31
Science cannot describe things that a.) are beyond imagination, experience, or human ability b.) cannot be observed, measured, or tested c.) have not been conclusively proven d.) occur without being seen, heard, or felt
Answers: 1
question
Social Studies, 23.06.2019 14:00
We belong to many different social groups that are made up of people that we interact with regularly. choose one of the following social groups: family friends co workers which social group has influenced you the most? in what ways?
Answers: 1
question
Social Studies, 23.06.2019 18:40
What is an example of the federal governments implied powers
Answers: 2
You know the right answer?
Based on the information in the passage, what is the most likely reason the Grand Coulee Dam took lo...
Questions
question
English, 21.04.2021 21:30
question
History, 21.04.2021 21:30
question
Computers and Technology, 21.04.2021 21:30
question
Mathematics, 21.04.2021 21:30