If the cost estimate for a project is a basis for contract awards and performance reporting, it should be a(n) estimate and as accurate as possible. select one:
a. rough order of magnitude
b. definitive
c. budgetary
d. analogous

ansver
Answers: 1

Another question on Physics

question
Physics, 22.06.2019 01:00
Calculate the amount of heat produced when 18000 coulombs of charge is transferred in one hour through a potential difference of 50v
Answers: 3
question
Physics, 22.06.2019 05:00
Wavelength,frequency,and energy are related.what happens to a wave as it’s wavelength gets shorter?
Answers: 2
question
Physics, 22.06.2019 07:20
If the ama of the inclined plane below is 2, calculate the ima and efficiency. ima = efficiency =
Answers: 1
question
Physics, 22.06.2019 11:30
If the chemical properties of a substance remain unchanged and appearance or shape of a substance changes it is called a ?
Answers: 1
You know the right answer?
If the cost estimate for a project is a basis for contract awards and performance reporting, it shou...
Questions