GIVING BRAINLIEST PLEASE HELP A special drill is used at a construction site to dig holes. A hole is dug to a depth of 2.75 feet when the drill hits rock. The progress slows to 56 feet per hour of digging. The depth of the hole must be at least 1012 feet by the end of the day to stay on schedule.

What is the minimum amount of time the drill must continue at its present rate to complete the hole on schedule?

Select from the drop-down menus to correctly complete the statement.

The drill requires at least
Choose...
hours and
Choose...
minutes to complete the hole on schedule.

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 20.06.2019 18:04
The parking lot of a store has the shape shown. all angles are right angles. what is the area of the parking lot?
Answers: 2
question
Mathematics, 21.06.2019 16:10
Abox contains 1 plain pencil and 4 pens. a second box contains 5 color pencils and 5 crayons. one item from each box is chosen at random. what is the probability that a plain pencil from the first box and a color pencil from the second box are selected? write your answer as a fraction in simplest form.
Answers: 1
question
Mathematics, 21.06.2019 17:00
How many credit hours will a student have to take for the two tuition costs to be equal? round the answer to the nearest tenth of an hour.
Answers: 1
question
Mathematics, 21.06.2019 20:30
Find the magnitude, correct to two decimal places, made by each of the following with positive direction of the x axis a) y= x the answer is 45° but i don’t know how
Answers: 2
You know the right answer?
GIVING BRAINLIEST PLEASE HELP A special drill is used at a construction site to dig holes. A hole...
Questions
question
Mathematics, 01.07.2019 17:30
question
Biology, 01.07.2019 17:30
question
History, 01.07.2019 17:30