if 20 persons are required to complete work in 24 days in how many days 15 persons finish the work ?

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 18:10
Which of these sequences is a geometric sequence a 1,2,4, 7, 11, 16, 22. b. 2.4.8.14.22.38 c.3.6.9. 15.18,21 d. 3,9,27,81,243,729,
Answers: 1
question
Mathematics, 21.06.2019 18:30
Agraphic designer created a logo on eight and a half by 11 inch paper. in order to be placed on a business card, the logo needs to be one and 7/10 inches by 2 and 1/5 in. what is the scale factor of the dilation
Answers: 1
question
Mathematics, 21.06.2019 19:00
[10 points, algebra 2]according to my answer key the restrictions are -1 and 4. but why not positive 1?
Answers: 1
question
Mathematics, 21.06.2019 21:00
Gabriel determined that his total cost would be represented by 2.5x + 2y – 2. his sister states that the expression should be x + x + 0.5x + y + y – 2. who is correct? explain.
Answers: 3
You know the right answer?
if 20 persons are required to complete work in 24 days in how many days 15 persons finish the work ?...
Questions
question
Social Studies, 05.05.2020 00:08
question
Mathematics, 05.05.2020 00:08
question
Mathematics, 05.05.2020 00:08
question
History, 05.05.2020 00:08