Working together, Shawn and Hector can install a tile floor in 6 hours. It would take Shawn 9 hours to do the job alone. What is the value of r, Hectora's rate of work in part per hour?

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 16:30
Anyone know? will mark brainliest if correct!
Answers: 1
question
Mathematics, 21.06.2019 19:10
What is the quotient? x+5/ 3x²+4x+5 © 3x2 – 11 + x + s 3x – 11 + 60 x + 5 o 3x2 - 11 - 50 x + 5 3x – 11 - - x + 5
Answers: 3
question
Mathematics, 21.06.2019 21:30
Look at triangle wxy what is the length (in centimeters) of the side wy of the triangle?
Answers: 1
question
Mathematics, 21.06.2019 22:00
Simplify (4x^2 - 8xy + 2y^2) - (9x^2 - 4xy - 7y^2) a. -5x^2 + 4xy + 9y^2 b. -5x^2 - 4xy + 9y^2 c. -5x^2 + 12xy + 4y^2 d. -5x^2 - 4xy - 5y^2
Answers: 1
You know the right answer?
Working together, Shawn and Hector can install a tile floor in 6 hours. It would take Shawn 9 hours...
Questions
question
Mathematics, 05.10.2019 05:00