subject
Mathematics, 07.09.2021 23:50 adhitrfbvg

A project consists of five activities. Naturally the paint mixing precedes the painting activities. Also, both ceiling painting and floor sanding must be done prior to floor buffing. Optimistic Most Probable Pessimistic Activity Time (hr) Time (hr) Time (hr) Floor sanding 3 4 5 Floor buffing 1 2 3 Paint mixing 0.5 1 1.5 Wall painting 1 2 9 Ceiling painting 1 5.5 7 ​ Construct the PERT/CPM network for this problem on a rough paper. What is the expected completion time of this project? What is the probability that the project can be completed within 9 hr.?

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 20:00
You are shooting hoops after school and make 152 out of a total of 200. what percent of shots did you make? what percent did you miss? show proportion(s).
Answers: 1
question
Mathematics, 22.06.2019 00:20
Convert the number to decimal form. 12) 312five a) 82 b) 30 c) 410 d) 1560 13) 156eight a) 880 b) 96 c) 164 d) 110 14) 6715eight a) 53,720 b) 3533 c) 117 d) 152
Answers: 1
question
Mathematics, 22.06.2019 00:20
Three students, javier, sam, and corrine, participated in a fundraiser where people donated a certain amount of money per lap that the student ran. each student also had some initial donations that were collected before the run. the equations that represent each student's total donation, y, based on the number of laps ran, x, is shown below. match each equation with the correct rate of change for that student.
Answers: 1
question
Mathematics, 22.06.2019 02:00
What are linear equations? could'ya explain too me, ? ! and how do you see what graph is a proportional relationship?
Answers: 2
You know the right answer?
A project consists of five activities. Naturally the paint mixing precedes the painting activities....
Questions
question
Mathematics, 04.06.2021 07:50
question
Mathematics, 04.06.2021 07:50