Mathematics, 03.09.2021 07:10 yeidiyan9490

32 workers can complete a work in 30 days working 6 hours per day. How many days are required to complete the same work by 16 workers working 8 hours per day?

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 17:00
The size of a certain cell is 2.5*10^-9m. another cell is 1.5*10^3 times larger. how large is the larger cell in scientific notation?
Answers: 2
question
Mathematics, 21.06.2019 18:00
Yesterday i ran 5 miles. today, i ran 3.7 miles. did my percent increase, decrease or is it a percent error? plz i need
Answers: 2
question
Mathematics, 21.06.2019 21:30
Hannah paid $3.20 for 16 ounces of potato chips. hank paid $3.23 for 17 ounces of potato chips. who paid less per ounces?
Answers: 1
question
Mathematics, 21.06.2019 22:30
The track team ran a mile and a quarter during their practice how many kilometers did her team runs?
Answers: 1
You know the right answer?
32 workers can complete a work in 30 days working 6 hours per day. How many days are required to com...
Questions
question
Mathematics, 10.11.2020 18:10
question
Mathematics, 10.11.2020 18:10
question
Business, 10.11.2020 18:10
question
Mathematics, 10.11.2020 18:10