Mathematics, 11.08.2021 14:50 keymariahgrace85

Laxman and Virat together can complete a piece of work in 8 days and Laxman alone can complete it in 12 days in how many days would Bharat alone complete the work​

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 19:30
For what values of the variable x is the expression square root of 7x+14+ square root of 7-x a real number?
Answers: 1
question
Mathematics, 21.06.2019 23:20
Write the equations in logarithmic form 7^3=343
Answers: 1
question
Mathematics, 22.06.2019 00:00
Technicians have installed a center pivot, circular irrigator for a farm that covers 25 acres. a.) how long is the irrigation boom (in feet) from the center pivot to its farthest extent? b.) if the irrigation boom makes 4 full revolutions in a day, how many miles does the end of the boom travel in 5 days?
Answers: 1
question
Mathematics, 22.06.2019 01:00
Astudent drew a circle and two secant segment. he concluded that if pq ~= ps, then qr ~= st. do you agree with the student’s conclusion? why or why not?
Answers: 1
You know the right answer?
Laxman and Virat together can complete a piece of work in 8 days and Laxman alone can complete it in...
Questions