Mathematics, 09.08.2021 14:00 grace783

Invers proportion It take twelve workers tree weeks to complete four project.

Each project takes the same number of man-hours to complete.

a) t this rate, how long would it take fifteen workers to complete ten project? = 6 weeks

b) the ten project need to be completed in under four weeks. what is the minimum number of workers needed given that they a ll work at the s ame rate as the original workers? ( i know answer but in need xplaining ) :] B=D ( sorri ignore)
i have tutoring I Need this quickly

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 12:40
Which graph represents 2x-5y< 15
Answers: 1
question
Mathematics, 21.06.2019 18:00
Solve 2^x=32 and rewrite this equation in a logarithmic form
Answers: 2
question
Mathematics, 21.06.2019 18:00
Find the midpoint m of z1=(8+5i) and z2=(12+3i)
Answers: 1
question
Mathematics, 21.06.2019 20:30
Find the magnitude, correct to two decimal places, made by each of the following with positive direction of the x axis a) y= x the answer is 45° but i don’t know how
Answers: 2
You know the right answer?
Invers proportion It take twelve workers tree weeks to complete four project.

Each proj...
Questions
question
Physics, 18.10.2021 09:20
question
Mathematics, 18.10.2021 09:30