A construction project has four separate components that must be completed in order. The expected values and standard deviations of the completion times of the activities are listed below. Assuming that the four activities are independent, determine the expected value and standard deviation of the completion time of the project. Activity Expected Completion Time (Days) std. Dev.
1 17 6
2 12 3
3 26 4
4 7 2

Expected value of completion time of project =
Standard deviation of completion time of project =

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 17:00
Scarlet bought three pairs of sunglasses and two shirts for $81 and paula bought one pair of sunglasses and five shirts for $105 what is the cost of one pair of sunglasses and one shirt?
Answers: 2
question
Mathematics, 21.06.2019 17:30
The swimming pool is open when the high temperature is higher than 20∘c. lainey tried to swim on monday and thursday (which was 33 days later). the pool was open on monday, but it was closed on thursday. the high temperature was 30 ∘c on monday, but decreased at a constant rate in the next 33 days. write an inequality to determine the rate of temperature decrease in degrees celsius per day, d, from monday to thursday.
Answers: 3
question
Mathematics, 21.06.2019 20:30
Someone me what is the area of this figure? 18m 18m 8m 16m
Answers: 2
question
Mathematics, 21.06.2019 21:00
In the field of thermodynamics, rankine is the unit used to measure temperature. one can convert temperature from celsius into rankine using the formula , what is the temperature in celsius corresponding to r degrees rankine? a. 9/5(c - 273) b. 9/5(c + 273) c. 5/9( c - 273) d. 5/9( c + 273)
Answers: 1
You know the right answer?
A construction project has four separate components that must be completed in order. The expected va...
Questions
question
English, 05.05.2020 03:29
question
Mathematics, 05.05.2020 03:29
question
Mathematics, 05.05.2020 03:29