A project has the following activities and related data: Activity. Time (Weeks) Immediate Activity Predecessor Crash Most Most Most Cost Maximum Optimistic likely Pessimistic ($000) Crashable (a) (m) (C) per weeks week A None 1 3 11 3 1 00 None 4 5 6 4 1 С А 5 6 7 1 2 D А 4 5 12 1 2 1 E B 6 11 2 1 B 1 2 15 F 1 3 2 4 6 6 G CD 2 3 4 2 1 2 H EF G CD 2 4 6 6 N H EF 2 3 3 4 4 2 1 34a. (20 points)
a. Compute the expected value E(t) and variance V(t) for all activities
Activity A B C D E F G H
E(t) weeks
V(t) weeks^2
b. there are three critical paths ACG, ADG, and BEH, all with expected project completion time time E(t) = 14 weeks. Compute the variance of project completion time for each path
V(ACG)=
V(ADG)=
V(BEH)
c. Assume that the project completion time T is normally distributed with mean E(T)=14 weeks and variance V(T) approximately by the maximum of the variances of the three individual critical paths. Determine the time X in weeks for which there is a 40% probability that the project can be completed on or before x.
d. List all alternatives and the respective costs for shortening the project by one week and identify the best alternative that has the minimum costs. Hint there are 8 alternatives
Alternative cost
the best alternative is..
e. For activity i, let Xi be the earliest finishing time and Yi be the number of weeks shortened. Formulate the linear program for minimizing the cost for shortening the project by one week
Answers: 2
Mathematics, 21.06.2019 19:30
Abird on top of a 200 ft bridge tower sees a man standing on the lower part of the bridge (which is 50 ft above the ground). the angle of depression from the bird is 26 ̊. how far is the man from the base of the bridge tower? with explanation and pictures .
Answers: 1
Mathematics, 21.06.2019 19:40
Which system of linear inequalities is represented by the graph?
Answers: 1
Mathematics, 21.06.2019 20:00
A. what does the point (4, 122) represent? b. what is the unit rate? c. what is the cost of buying 10 tickets?
Answers: 2
Mathematics, 21.06.2019 23:30
Tim earns $120 plus $30 for each lawn he mows.write an iniqualityvto represent how many lawns he needs to mow to make more than $310
Answers: 2
A project has the following activities and related data: Activity. Time (Weeks) Immediate Activity P...
Computers and Technology, 06.05.2021 06:40
Mathematics, 06.05.2021 06:40
Mathematics, 06.05.2021 06:40
History, 06.05.2021 06:40
Mathematics, 06.05.2021 06:40
Mathematics, 06.05.2021 06:40
Computers and Technology, 06.05.2021 06:40
Chemistry, 06.05.2021 06:40
History, 06.05.2021 06:50