Two plumbers received a job. At first, one of the plumbers worked alone for 1 hour, and then they worked together for the next 4 hours. After this 40% of the job was complete. How long would it take each plumber to do the whole job by himself if it is known that the first plumber would take 5 more hours to finish the job than the second plumber?

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 23:20
Using only the digits 5, 6, 7, 8, how many different three digit numbers can be formed if no digit is repeated in a number?
Answers: 1
question
Mathematics, 22.06.2019 00:00
Afarmer has decided to divide his land area in half in order to plant soy and corn. calculate the area of the entire area so he knows how much soil is needed. each bag of soil covers 20 square yards. how many bags should the farmer purchase? (4 points) 1 bag 2 bags 3 bags 4 bags
Answers: 2
question
Mathematics, 22.06.2019 00:00
Abook store is having a 30 perscent off sale. diary of the wimpy kid books are now 6.30 dollars each what was the original price of the books
Answers: 1
question
Mathematics, 22.06.2019 01:50
:i need some real : a store sells shirts to the public at one pricing scale and wholesale at another pricing scale. the tables below describe the cost, y, of x shirts. (after tables) how do the slopes of the lines created by each table compare? the slope of the public table is 3/4 of the slope of the wholesale table.the slope of the wholesale table is 3/4 of the slope of the public table.the slope of the public table is 12 times greater than the slope of the wholesale table.the slope of the wholesale table is 12 times greater than the slope of the public table.
Answers: 3
You know the right answer?
Two plumbers received a job. At first, one of the plumbers worked alone for 1 hour, and then they wo...
Questions
question
Mathematics, 26.11.2020 04:00