There are four activities on the critical path, and they have standard deviations of 1, 2, 4, and 2. what is the probability that the project will be completed in 38 weeks if its expected completion time is 40 weeks?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 14:00
Arandom number generator is used to model the patterns of animals in the wild this type of study is called
Answers: 1
question
Mathematics, 21.06.2019 14:00
Toyland is having a sale. all items are 20% off. how much will you save on an item that usually sells for 95$ explain your
Answers: 1
question
Mathematics, 21.06.2019 19:00
After t seconds, a ball tossed in the air from the ground level reaches a height of h feet given by the equation h = 144t-16t^2. after how many seconds will the ball hit the ground before rebounding?
Answers: 2
question
Mathematics, 21.06.2019 23:40
Will give brainliest b. describe the function over each part of its domain. state whether it is constant, increasing, or decreasing, and state the slope over each part.
Answers: 1
You know the right answer?
There are four activities on the critical path, and they have standard deviations of 1, 2, 4, and 2....
Questions
question
Computers and Technology, 29.10.2020 01:40
question
Biology, 29.10.2020 01:40
question
Mathematics, 29.10.2020 01:40
question
Mathematics, 29.10.2020 01:40
question
Computers and Technology, 29.10.2020 01:40
question
English, 29.10.2020 01:40
question
Mathematics, 29.10.2020 01:40
question
Mathematics, 29.10.2020 01:40