Mathematics, 19.10.2019 16:00 andrew763

Amanufacturing company plans to progressively increase its production capacity over the next few quarters. (a quarter is a period of three months.) the increase in production can be modeled by the equation y = x6 − 25x4 + 199x2, where x is the number of quarters. what is the minimum duration required for the company to reach a production capacity of 4,975 units?

a)4 quarters
b)5 quarters
c)6 quarters
d)7 quarters

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 14:30
Atriangular bandana has an area of 46 square inches. the height of the triangle is 5 3 4 inches. enter and solve an equation to find the length of the base of the triangle. use b to represent the length of the base.
Answers: 2
question
Mathematics, 21.06.2019 15:30
The function Æ’ is defined by Æ’(x) = (x + 3)(x + 1). the graph of Æ’ in the xy-plane is a parabola. which interval contains the x-coordinate of the vertex of the graph of Æ’?
Answers: 2
question
Mathematics, 21.06.2019 16:30
If 20% of a number is 35, what is 50% of that number?
Answers: 2
question
Mathematics, 21.06.2019 20:00
Evaluate the discriminant of each equation. tell how many solutions each equation has and whether the solutions are real or imaginary. x^2 + 4x + 5 = 0
Answers: 2
You know the right answer?
Amanufacturing company plans to progressively increase its production capacity over the next few qua...
Questions
question
Mathematics, 22.08.2020 21:01