A factory begins the day with 6,000 packaged light bulbs. The machines in the factory can package 1,200 light bulbs every hour for the next 5 hours. ​ ​
​The initial value of this function is

and the rate of change is

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 17:30
What term makes it inconsistent y=2x - 4 ?
Answers: 3
question
Mathematics, 21.06.2019 22:30
The median for the given set of six ordered data values is 29.5 9 12 25 __ 41 48 what is the missing value?
Answers: 1
question
Mathematics, 22.06.2019 01:00
Atriangle has side lengths of x, x+11, and 3x+5. what is the perimeter?
Answers: 1
question
Mathematics, 22.06.2019 01:20
The ratio of the height of two similar cylinders is 4 to 3 what is the ratio of their volumes
Answers: 1
You know the right answer?
A factory begins the day with 6,000 packaged light bulbs. The machines in the factory can package 1,...
Questions
question
Mathematics, 29.01.2021 06:10
question
Mathematics, 29.01.2021 06:10
question
Advanced Placement (AP), 29.01.2021 06:10
question
Mathematics, 29.01.2021 06:10
question
English, 29.01.2021 06:10