For a large hotel construction job, a group of 11 workers completed 33 rooms in four weeks. If the company has to complete 57 rooms in the next four weeks, and the workers work at the same rate, how many workers are needed?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 12:30
Started: jun 20 at 10: 35pm quiz instructions question 3 y 2x+4 graph the system of linear inequalities 1 by < 2x-2 ty
Answers: 3
question
Mathematics, 21.06.2019 15:50
If the dimensions of a rectangular prism are 5 ft x 3.5 ft x 2 Å¿t, what is the surface area?
Answers: 1
question
Mathematics, 21.06.2019 19:30
Evaluate the expression for the given value of the variable. ∣-4b-8∣+∣-1-b^2 ∣+2b^3 ; b=-2
Answers: 2
question
Mathematics, 21.06.2019 19:30
Which of the following transformations will always produce a congruent figure?
Answers: 2
You know the right answer?
For a large hotel construction job, a group of 11 workers completed 33 rooms in four weeks. If the c...
Questions
question
History, 22.11.2019 23:31