Rashid can do a piece of work in 8 days, which Tipu can finish in 12 days. If they work on alternate days with Rashid Beginning, in how many days, the work will be finished?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 17:20
Aboat costs 19200 and decreases in value by 12% per year. how much will it cost in 5 years
Answers: 2
question
Mathematics, 21.06.2019 18:30
Can someone check if i did this right since i really want to make sure it’s correct. if you do you so much
Answers: 2
question
Mathematics, 21.06.2019 20:00
Landon wrote that 3−2.6=4. which statement about his answer is true?
Answers: 1
question
Mathematics, 21.06.2019 21:30
Acoffee shop orders at most $3,500 worth of coffee and tea. the shop needs to make a profit of at least $1,900 on the order. the possible combinations of coffee and tea for this order are given by this system of inequalities, where c = pounds of coffee and t = pounds of tea: 6c + 13t ≤ 3,500 3.50c + 4t ≥ 1,900 which graph's shaded region represents the possible combinations of coffee and tea for this order?
Answers: 1
You know the right answer?
Rashid can do a piece of work in 8 days, which Tipu can finish in 12 days. If they work on alternate...
Questions
question
Mathematics, 31.08.2021 15:20
question
Mathematics, 31.08.2021 15:20
question
Social Studies, 31.08.2021 15:30