The time to build a house varies inversely with the square root of the number of people working. If 16 people can build a house in 100 days, then how long would it take 64 people?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 20:00
Credit card a offers an introductory apr of 3.4% for the first three months and standard apr of 15.7% thereafter,
Answers: 3
question
Mathematics, 21.06.2019 22:30
What is the common difference for this arithmetic sequence? -6,-2,2,6,10 a.4 b.5 c.3 d.6
Answers: 1
question
Mathematics, 21.06.2019 23:20
1. ∠1 is complementary to ∠2 and ∠3 is complementary to ∠2. subtraction property of equality 2. m∠1 + m∠2 = 90 and m∠3 + m∠2 = 90 substitution 3. m∠1 + m∠2 = m∠3 + m∠2 definition of complementary 4. m∠1 = m∠3 given
Answers: 3
question
Mathematics, 22.06.2019 01:00
X^2/100+y^2/25=1 the y-intercepts are at: a) (-10,0) and (10,0) b) (0,10) and (0,5) c) (0,-5) and (0,5)
Answers: 1
You know the right answer?
The time to build a house varies inversely with the square root of the number of people working. If...
Questions