Mathematics, 13.12.2020 23:40 savyblue1724707

How many workers will be needed to complete a task in 16 days, given that 8 workers can complete the same task in 12 days?

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 16:00
Find the greatest common factor of the polynomial: 10x^5+15x^4-25x^3 10x^5 x^3 5x^3 5
Answers: 2
question
Mathematics, 21.06.2019 17:30
Triangle xyz has vertices x(1,3), y(0,0)
Answers: 1
question
Mathematics, 21.06.2019 17:30
What term makes it inconsistent y=2x - 4 ?
Answers: 3
question
Mathematics, 21.06.2019 18:30
Dakota earned $7.50 in interest in account a and $18.75 in interest in account b after 15 months. if the simple interest rate is 4% for account a and 5% for account b, which account has the greater principal? explain. to make it a little easier, there is an image. good luck!
Answers: 1
You know the right answer?
How many workers will be needed to complete a task in 16 days, given that 8 workers can complete the...