8,000 workers were employed by a company to complete a job in 4 years. At the end of first year,
5% of the workers were retrenched. At the end of
second year, 5% of those working at that time were
retrenched. However to complete the job in time, the
number of workers was increased by 10% of those
working at the end of third year. How many workers
were working during the fourth year?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 15:00
Two lines parallel to a third line are parallel to each other. always sometimes or never
Answers: 1
question
Mathematics, 21.06.2019 17:30
8000 + 8800 + 8000 + 8 million + 80 trillion + another a katrillion equals
Answers: 1
question
Mathematics, 21.06.2019 18:00
Need on this geometry question. explain how you did it.
Answers: 2
question
Mathematics, 21.06.2019 22:30
Tommy buys a sweater that is on sale for 40% off the original price. the expression p -0.4p can be used to find the sale price of the sweater, where p is the original price of the sweater. if the original price of the sweater is 50, what is the sale price?
Answers: 1
You know the right answer?
8,000 workers were employed by a company to complete a job in 4 years. At the end of first year,
Questions
question
Mathematics, 12.09.2019 04:30