Mathematics, 26.06.2020 15:01 karlyisaunicorn
It took $4$ days for $75$ workers, all working together at the same rate, to build an embankment. If only $50$ workers had been available, how many total days would it have taken to build the embankment?
Answers: 2
Mathematics, 20.06.2019 18:02
Name the type of angle shown.calculation tip: common types of angles are zero, straight, right, acute, or obtuse.
Answers: 2
Mathematics, 21.06.2019 16:20
Which math sentence can be used to determine if the triangle is a right triangle?
Answers: 1
Mathematics, 21.06.2019 19:00
When keisha installed a fence along the 200 foot perimeter of her rectangular back yard, she left an opening for a gate.in the diagram below, she used x to represent the length in feet of the gate? what is the value? a. 10 b. 20 c. 25 d. 30
Answers: 1
It took $4$ days for $75$ workers, all working together at the same rate, to build an embankment. If...
Computers and Technology, 18.07.2020 22:01
Mathematics, 18.07.2020 22:01
Mathematics, 18.07.2020 22:01
Mathematics, 18.07.2020 22:01
Physics, 18.07.2020 22:01
Computers and Technology, 18.07.2020 22:01
Computers and Technology, 18.07.2020 22:01