The following table provides a description for the project Z. Activity Duration Predecessor Cost to crash Max Days
by 1 day to Crash
A 5 - $ 300 1
B 3 - $ 100 1
C 4 A $ 100 1
D 3 A $ 200 2
E 4 B $ 400 3
F 2 D, E $ 500 2
G 4 E $ 300 3
H 3 C $ 100 2
A. What is the critical path of this project?
The following table provides a description for the project Z.
Activity/ Duration/ Predecessor/ Cost to crash Max Days
by 1 day/ to Crash
A 5 - $ 300 1
B 3 - $ 100 1
C 4 A $ 100 1
D 3 A $ 200 2
E 4 B $ 400 3
F 2 D, E $ 500 2
G 4 E $ 300 3
H 3 C $ 100 2
B. What is the duration of this project?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 16:30
I’m which figure is point g an orthocenter
Answers: 1
question
Mathematics, 21.06.2019 17:00
Given that ot =5, xt=12, and ox= 13 is xy tangent to circle o at t? explain.
Answers: 1
question
Mathematics, 21.06.2019 17:00
Which expression is equivalent to 8(k + m) − 15(2k + 5m)?
Answers: 1
question
Mathematics, 21.06.2019 20:20
Convert the mixed numbers into improper fractions. convert the improper fraction to mixed numbers.
Answers: 1
You know the right answer?
The following table provides a description for the project Z. Activity Duration Predecessor Cost to...
Questions
question
Mathematics, 27.09.2021 14:00
question
Social Studies, 27.09.2021 14:00
question
Mathematics, 27.09.2021 14:00
question
Mathematics, 27.09.2021 14:00
question
Mathematics, 27.09.2021 14:00
question
Social Studies, 27.09.2021 14:00