09 men can complete a work in 04 days, how many men are needed to complete the same work in 06 days.

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 14:00
Algebra 1: unit 6 part 2 of test a) the table shows a linear function. x 0 1 2 3 5 13 21 29 37 45 53 (a) determine the difference of outputs of any two inputs that are 1 unit apart. show your work. (b) determine the difference of outputs of any two inputs that are 2 units apart. show your work.
Answers: 2
question
Mathematics, 21.06.2019 18:00
What set does not contain -3 the set of all real numbers the set of all integers the set of all whole numbers the set of all rational numbers
Answers: 1
question
Mathematics, 21.06.2019 21:00
Which must be true in order for the relationship △zyv ~ △xwv to be correct? zy ∥ wx ∠z ≅ ∠y and ∠w ≅ ∠x zv ≅ vy and wv ≅ vx ∠z ≅ ∠x and ∠w ≅ ∠y
Answers: 2
question
Mathematics, 22.06.2019 01:00
The triangles are similar. what is the value of x? enter your answer in the box.
Answers: 1
You know the right answer?
09 men can complete a work in 04 days, how many men are needed to complete the same work in 06 days....
Questions
question
Mathematics, 16.02.2020 11:23
question
English, 16.02.2020 11:28