Suppose it is now the end of the seventh day and that activities A and B have been completed while activity D is 50 percent completed. Time estimates for the completion of activity D are 5, 6, and 7. Activities C and H are ready to begin. Determine the probability of finishing the project by day 24 and the probability of finishing by day 21.

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 15:30
The equation respenting the left table is
Answers: 2
question
Mathematics, 21.06.2019 17:40
Find the value of x that will make l ll m
Answers: 2
question
Mathematics, 21.06.2019 20:00
How many sides does a regular polygon have if each exterior angle measure is 45 degrees explain your answer, i really don't understand this.
Answers: 1
question
Mathematics, 22.06.2019 02:00
The first term of a sequence is -12. the recursive formula for the sequence is an = an-1 + 9. what are the next 3 terms in the sequence? a) -3, -15, -27 b) -3, 6, 15 c) -3, -6, -3 d) -3, -6, 3
Answers: 2
You know the right answer?
Suppose it is now the end of the seventh day and that activities A and B have been completed while a...
Questions
question
Mathematics, 27.06.2020 19:01
question
Mathematics, 27.06.2020 19:01