subject
Mathematics, 22.04.2020 23:24 scholar13

An activity has a pessimistic time that is four times as long as its most likely time and six times as long as its optimistic time. If the activity variance is 12, what is the expected time?

A) About 8 days

B) About 9 days

C) About 10 days

D) About 11 days

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 17:40
Aline has a slope of and a y-intercept of –2. what is the x-intercept of the line?
Answers: 1
question
Mathematics, 21.06.2019 19:20
Find the area of an equilateral triangle with a side of 6 inches
Answers: 2
question
Mathematics, 21.06.2019 20:30
10 points? me . its important ‼️‼️
Answers: 1
question
Mathematics, 22.06.2019 04:00
What is being done to the variable in the equation 3 + g = -9? the number 3 is being added to it. the number 3 is being subtracted from it. the number -9 is being added to it. the number -9 is being subtracted from it.
Answers: 2
You know the right answer?
An activity has a pessimistic time that is four times as long as its most likely time and six times...
Questions
question
Mathematics, 28.09.2019 02:30
question
Mathematics, 28.09.2019 02:30
question
Mathematics, 28.09.2019 02:30