You are planning to use PERT for planning of your project. A task has pessimistic estimate of 24 days, most likely estimate of 15 days and optimistic estimate of 12 days. What is the mean using the PERT technique?
a.18 days
b.25.5 days
c.15 days
d.16 days

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 18:00
Ageologist had two rocks on a scale that weighed 4.6 kilograms together.rock a was 0.5 of the total weight.how much did rock a weigh?
Answers: 1
question
Mathematics, 22.06.2019 00:00
What else equals 42 and 30 for multiply
Answers: 1
question
Mathematics, 22.06.2019 02:30
The upcoming championship high school football game is a big deal in your little town. the problem is, it is being played in the next biggest town, which is two hours away! to get as many people as you can to attend the game, you decide to come up with a ride-sharing app, but you want to be sure it will be used before you put all the time in to creating it. you determine that if more than three students share a ride, on average, you will create the app. you conduct simple random sampling of 20 students in a school with a population of 300 students to determine how many students are in each ride-share (carpool) on the way to school every day to get a good idea of who would use the app. the following data are collected: 6 5 5 5 3 2 3 6 2 2 5 4 3 3 4 2 5 3 4 5 construct a 95% confidence interval for the mean number of students who share a ride to school, and interpret the results. part a: state the parameter and check the conditions. part b: construct the confidence interval. be sure to show all your work, including the degrees of freedom, critical value, sample statistics, and an explanation of your process. part c: interpret the meaning of the confidence interval. part d: use your findings to explain whether you should develop the ride-share app for the football game.
Answers: 3
question
Mathematics, 22.06.2019 05:00
Of the 189 miles of beaches at ocean side, 7% are privately owned 39% are owned by resorts, and 54% are public beaches. how many miles of beach are not public?
Answers: 2
You know the right answer?
You are planning to use PERT for planning of your project. A task has pessimistic estimate of 24 day...
Questions
question
Mathematics, 26.08.2019 20:10
question
Mathematics, 26.08.2019 20:10
question
Mathematics, 26.08.2019 20:10
question
Geography, 26.08.2019 20:10