Mathematics, 20.04.2020 00:56 anggar20

A piece of manufacturing equipment can produce enough items to fill an order in 10 hours. If an auxiliary piece of equipment is used also, it will take 7 hours. How long would it take the auxillary equipment to fill the order working alone?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 16:00
What is the solution to the system of equations? (–2, –8) (–1, –5) (0, –2) (2, 4)
Answers: 3
question
Mathematics, 21.06.2019 16:10
The number of hours per week that the television is turned on is determined for each family in a sample. the mean of the data is 37 hours and the median is 33.2 hours. twenty-four of the families in the sample turned on the television for 22 hours or less for the week. the 13th percentile of the data is 22 hours. approximately how many families are in the sample? round your answer to the nearest integer.
Answers: 1
question
Mathematics, 21.06.2019 22:20
Solve the formula ax+ by = c for x.
Answers: 2
question
Mathematics, 21.06.2019 23:10
Pls yall i really need the answer fr fr
Answers: 1
You know the right answer?
A piece of manufacturing equipment can produce enough items to fill an order in 10 hours. If an auxi...
Questions
question
Chemistry, 05.10.2020 14:01
question
Mathematics, 05.10.2020 14:01
question
Mathematics, 05.10.2020 14:01
question
Biology, 05.10.2020 14:01