Completion time (from start to finish) of a building remodeling project is normally distributed with a mean of 200 work-days and a standard deviation of 10 work-days. The probability that the project will be completed within 185 work-days is

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 17:30
Asphere has a diameter of 10 in. what is the volume of the sphere?
Answers: 1
question
Mathematics, 21.06.2019 19:30
Anna is constructing a line segment that is congruent to another segment ab. for the construction, which tool should be used to mesure segment ab
Answers: 1
question
Mathematics, 21.06.2019 22:00
Apackage of five erasers cost 0. $.39 at this rate how many how much would 60 erasers cost in dollars and cents
Answers: 2
question
Mathematics, 21.06.2019 23:30
Marking brainliest rewrite the equation x = 65 - 60p by factoring the side that contains the variable p.
Answers: 3
You know the right answer?
Completion time (from start to finish) of a building remodeling project is normally distributed with...
Questions
question
Mathematics, 29.01.2020 23:52
question
Geography, 29.01.2020 23:52