The time required to complete a project is normally distributed with a mean of 80 weeks and a standard deviation of 10 weeks. The construction company must pay a penalty if the project is not finished by the due date in the contract. If a construction company bidding on this contract wishes to be 90 percent sure of finishing by the due date, what due date (project week #) should be negotiated?
Answers: 3
Mathematics, 21.06.2019 19:00
Amodel rocket is launched from a roof into a large field. the path of the rocket can be modeled by the equation y = -0.04x^2 + 8.6x + 4.8, where x is the horizontal distance, in meters, from the starting point on the roof and y is the height, in meters, of the rocket above the ground. how far horizontally from its starting point will the rocket land? a. 0.56 m b. 215.56 m c. 431.11 m d. 215.74 m
Answers: 1
Mathematics, 21.06.2019 19:30
The figure below shows rectangle abcd and the triangle eca on a coordinate plane.which of the following expressions represents the perimeter of triangle of triangle eca in units
Answers: 2
Mathematics, 21.06.2019 23:00
Hormones perform important functions within the reproductive system. during puberty, a number of changes occur in the body. which hormone is responsible for the development of these characteristics in the female? estrogen progestin progesterone testosterone
Answers: 1
The time required to complete a project is normally distributed with a mean of 80 weeks and a standa...
Mathematics, 29.08.2019 05:30
Biology, 29.08.2019 05:30
Computers and Technology, 29.08.2019 05:30
History, 29.08.2019 05:30
English, 29.08.2019 05:30
English, 29.08.2019 05:30
Biology, 29.08.2019 05:30
Mathematics, 29.08.2019 05:30
History, 29.08.2019 05:30
Mathematics, 29.08.2019 05:30