In the following Earliest Start Time (EST) graph, assume each unit of time is an hour.

What is the critical path and the minimum project time? (hint: this is the longest path).

CEFH, 21 hours

BEFH, 21 hours

ADFH, 21 hours

both B and C


In the following Earliest Start Time (EST) graph, assume each unit of time is an hour.  What is the

ansver
Answers: 3

Another question on Mathematics

question
Mathematics, 21.06.2019 16:00
Use set buikder notation to represent the following set: {, -2, -1, 0}
Answers: 1
question
Mathematics, 21.06.2019 16:30
To which set of numbers does the number –5 belong? select all that apply. integers natural numbers rational numbers real numbers whole numbers
Answers: 1
question
Mathematics, 21.06.2019 18:00
Me asap! what is the slope of this line? enter your answer in the box.
Answers: 2
question
Mathematics, 21.06.2019 18:30
Select the lengths in centimeters that would form a right triangle
Answers: 1
You know the right answer?
In the following Earliest Start Time (EST) graph, assume each unit of time is an hour.

...
Questions
question
Computers and Technology, 14.07.2020 01:01
question
Mathematics, 14.07.2020 01:01
question
Mathematics, 14.07.2020 01:01
question
English, 14.07.2020 01:01
question
Mathematics, 14.07.2020 01:01