subject
Mathematics, 13.02.2020 20:25 blackops3318

The activity completion time of each of the 5 critical activities of a project follows normal distribution. If the mean activity completion time of each activity is 2 weeks, and the standard deviation of the activity completion time of each of the critical activity is 10, then what is the probability that the project would take between 9 and 13 week?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 16:20
Plot the points (0,6), (3,15.8), and (9.5,0) using the graphing tool, and find the function
Answers: 2
question
Mathematics, 21.06.2019 18:00
What set does not contain -3 the set of all real numbers the set of all integers the set of all whole numbers the set of all rational numbers
Answers: 1
question
Mathematics, 21.06.2019 18:30
Aswimming pool had 2.5 million liters of water in it. some water evaporated, and then the pool only had 22 million liters of water in it. what percent of the water evaporated?
Answers: 1
question
Mathematics, 21.06.2019 20:10
Suppose g(x) = f(x + 3) + 4. which statement best compares the graph of g(x) with the graph of f(x)?
Answers: 2
You know the right answer?
The activity completion time of each of the 5 critical activities of a project follows normal distri...
Questions
question
English, 09.07.2021 02:40
question
Mathematics, 09.07.2021 02:40
question
Mathematics, 09.07.2021 02:40
question
Mathematics, 09.07.2021 02:40
question
Mathematics, 09.07.2021 02:40