Each x requires 2 of component y; each y requires 4 of part z. the lead time for assembly of x is 1 week. the lead time for the manufacture of y is 1 week. the lead time for the procurement of z is 6 weeks. the cumulative lead time for x is weeks.
a. 48
b. 7
c. 8
d. 10

ansver
Answers: 2

Another question on Mathematics

question
Mathematics, 21.06.2019 17:30
What is the 12th term of b(n)=-4-2(n-1)
Answers: 1
question
Mathematics, 21.06.2019 19:00
Which table represents a linear function? i'll give brainliest to first answer ^'^
Answers: 1
question
Mathematics, 21.06.2019 19:10
What is the quotient? x+5/ 3x²+4x+5 © 3x2 – 11 + x + s 3x – 11 + 60 x + 5 o 3x2 - 11 - 50 x + 5 3x – 11 - - x + 5
Answers: 3
question
Mathematics, 21.06.2019 21:30
How many terms does the polynomial x^2 y^2 have
Answers: 1
You know the right answer?
Each x requires 2 of component y; each y requires 4 of part z. the lead time for assembly of x is 1...
Questions
question
Mathematics, 20.07.2019 16:00