Mathematics, 08.08.2019 03:10 anggar20
Using johnson's rule for 2-machine scheduling, the sequence is: six jobs are to be processed through a two-step operation. the first operation involves sanding, and the second involves painting. processing times are as follows scheduled order job operation 1 (hours) 12 operation 2 (hours) job 10 for the schedule developed using johnson's rule, the total length of time taken to complete the six jobs (including the 2nd operation)- 51 hours (enter your response as a whole number).
Answers: 3
Mathematics, 21.06.2019 13:00
Use this data in the problem below. follow the steps carefully. round to the nearest tenth. lot 3: week 1: 345 week 2: 340 week 3: 400 week 4: 325 step 1. jim enters the data and calculates the average or mean. step 2. jim calculates the deviation from the mean by subtracting the mean from each value. step 3. jim squares each deviation to remove negative signs. step 4. jim sums the squares of each deviation and divides by the count for the variance. step 5. jim takes the square root of the variance to find the standard deviation.
Answers: 2
Mathematics, 21.06.2019 19:30
Richard save $32 in march he saved $48 in april and $38 in may then richard spent $113 on a keyboard how much money does richard have left
Answers: 1
Mathematics, 21.06.2019 21:30
Consider circle c with angle acb measuring 3/4 radians.if minor arc ab measures 9 inches, what is the length of the radius of circle c? if necessary, round your answer to the nearest inch.
Answers: 2
Using johnson's rule for 2-machine scheduling, the sequence is: six jobs are to be processed throug...
Social Studies, 23.06.2021 20:10
History, 23.06.2021 20:10
Mathematics, 23.06.2021 20:10
Biology, 23.06.2021 20:10
Mathematics, 23.06.2021 20:10
Biology, 23.06.2021 20:10
Business, 23.06.2021 20:10