It takes 14 electricians 18 days to wire a new housing subdivision. how many days would it take 24 electricians to do the same job?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 15:00
1. are the triangles similar and if so why? what is the value of x? show your work.
Answers: 2
question
Mathematics, 21.06.2019 15:30
The weight of an object in a particular scale is 175.2 lbs. the measured weight may vary from the actual weight by at most 0.1 lbs. what is the range of actual weights of the object
Answers: 3
question
Mathematics, 21.06.2019 18:30
For each polynomial, determine the degree and write the polynomial in descending order. a. –4x^2 – 12 + 11x^4 b. 2x^5 + 14 – 3x^4 + 7x + 3x^3
Answers: 2
question
Mathematics, 21.06.2019 22:00
Nikita wants to apply for student aid to fund her college education. arrange the steps involved in nikita’s application for financial aid
Answers: 3
You know the right answer?
It takes 14 electricians 18 days to wire a new housing subdivision. how many days would it take 24 e...
Questions
question
Mathematics, 18.04.2021 19:20