subject
Mathematics, 07.07.2019 16:00 smartperraorwhateva

Aplumbing contractor bid the rough-in work for a new three-story office building based an estimate of 850 hours of a journey-level plumber's time on the job. after the job was in progress, the contractor determined that the first floor required 342 hours and the second floor required 329 hours. how many labor hours are left in the estimate to complete the third floor?

ansver
Answers: 1

Another question on Mathematics

question
Mathematics, 21.06.2019 15:00
Which property is illustrated by the following statement? if hxa rgi, then rgi hxa.
Answers: 1
question
Mathematics, 21.06.2019 15:40
What term best describes a line ans a point that lie in the same plane
Answers: 3
question
Mathematics, 21.06.2019 17:30
The sum of two numbers is 12 and their difference is 18 what are the two numbers
Answers: 1
question
Mathematics, 21.06.2019 19:10
The linear combination method is applied to a system of equations as shown. 4(.25x + .5y = 3.75) → x + 2y = 15 (4x – 8y = 12) → x – 2y = 3 2x = 18 what is the solution of the system of equations? (1,2) (3,9) (5,5) (9,3)
Answers: 1
You know the right answer?
Aplumbing contractor bid the rough-in work for a new three-story office building based an estimate o...
Questions
question
Mathematics, 03.09.2021 07:40
question
Mathematics, 03.09.2021 07:40
question
Mathematics, 03.09.2021 07:40