If you are representing the owner/engineer, and during the bidding phase of a project, a bidder telephones your office calling attention to what the bidder believes to be an error, and makes a request for clarification or correction, you should: . A. check out the reported error while still on the telephone, give the caller the corrected data orally, then send an addenda to everyone e1se .
B. deny that an error exists and tell the caller to bid the work as it was specified and make his or her own interpretations.
C. take all of the information from the caller, then advise him or her to bid the job as it was originally specified unless an addenda is issued, and that if an error was in fact discovered, it will be corrected by addenda which will be mailed to all bidders.
D. try to be as helpful as possible by checking with the original designer; then, if an error is noted, give the caller the correct information, but do not go out of your way to inform others unless they call with the same question.

ansver
Answers: 2

Another question on Engineering

question
Engineering, 04.07.2019 18:10
The mass flow rate of the fluid remains constant in all steady flow process. a)- true b)- false
Answers: 1
question
Engineering, 04.07.2019 18:10
For the closed feedwater heater below, feedwater enters state 3 at a pressure of 2000 psia and temperature of 420 °f at a rate of ix10 ibhr. the feedwat extracted steam enters state 1 at a pressure of 1000 psia and enthalpy of 1500 btu/lbm. the extracted er leaves at an enthalpy of 528.7 btu/lbm steam leaves as a saturated liquid. (16) a) determine the mass flow rate of the extraction steam used to heat the feedwater (10) b) determine the terminal temperature difference of the closed feedwater heater
Answers: 3
question
Engineering, 04.07.2019 18:20
Aquick transition of the operating speed of a shaft from its critical speed will whirl amplitude. (a) increase (b) limit (c) not affect (d) zero
Answers: 2
question
Engineering, 06.07.2019 02:30
On solidification from a melt, the polymer polyethylene forms a semi-crystalline spherulite structure. (i) sketch an individual spherulite and label the amorphous and crystalline regions. (ii) draw a schematic to show the changes in specific volume with temperature during cooling from the melt, comparing it to the theoretical extremes of fully crystalline and fully amorphous (indicate tm and tg)
Answers: 2
You know the right answer?
If you are representing the owner/engineer, and during the bidding phase of a project, a bidder tele...
Questions
question
Mathematics, 07.09.2021 14:00
question
Health, 07.09.2021 14:00
question
Social Studies, 07.09.2021 14:00