Question # 6 Multiple Choice
The following excerpt is from a report for the Israel Institute of Technology by Ari Teger on high-rise construction.
There are many aspects involved in scheduling a construction project. Even a priori scheduling requires dealing with many interdependent
tasks and resources, and once the project starts the task is even more complex. Although the schedule can be created using calculations
like the one described earlier, construction doesn't actually proceed with such precision. Instead, it's best to either rely on assumptions or
calculations but then with the results adjusted according to experience and common sense. For instance, if a calculation results in a task
taking 0.9 of a workday, it isn't reasonable to assume that another task will be performed that day. There is a good chance that it will take
slightly longer than calculated, and once it's completed, workers will be ready to go home and won't be willing to start a percentage of a
task in the part of the workday that is remaining.
Why would a construction manager not try to increase efficiency by maximizing the amount of tasks on any given workday?
Construction managers shouldn't be involved in maximizing task efficiency; that's the foreman's job.
O Workers are most efficient when they have fewer tasks to handle.
Workers are incapable of truly working a full day.
The schedule he or she creates will not be realistic.

ansver
Answers: 1

Another question on Engineering

question
Engineering, 04.07.2019 16:10
The force on a cutting tool are 2600n vertically downward and 2100 horizontal. determine the resultant force acting on the tool and the angle at which it acts.
Answers: 1
question
Engineering, 04.07.2019 18:10
Different types of steels contain different elements that alter the characteristics of the steel. for each of the following elements, explain what the element does when alloyed with steel.
Answers: 2
question
Engineering, 04.07.2019 18:10
Journeyman training is usually related (clo2) a)-to specific tasks b)-to cost analysis of maintenance task c)-to control process to ensure quality d)-to installation of machinery
Answers: 2
question
Engineering, 04.07.2019 18:10
Machinery that is a key part of the process and without which the plant or process cannot function is classifed as: (clo4) a)-critical machinery b)-essential machinery c)-general purpose machinery d)-none of the specified options.
Answers: 1
You know the right answer?
Question # 6 Multiple Choice
The following excerpt is from a report for the Israel Institute...
Questions
question
Mathematics, 08.07.2019 09:00
question
Social Studies, 08.07.2019 09:00
question
Mathematics, 08.07.2019 09:00