In a standard 6-day period, the production department programme a specific machine to work for 250 hours- its loading time. Changeovers and set-ups take average of 8 hours and breakdown failures average 3 hours every 6 days.
The time when the machine cannot work because it is waiting for material to be delivered from other parts of the process is 1 hour on average and during the period when the machine is running, it averages 92 per cent of its rated speed.
Two per cent of the parts processed by the machine are subsequently found to be defective in some way.

Based on above data, calculate overall equipment effectiveness (OEE)

ansver
Answers: 1

Another question on Engineering

question
Engineering, 04.07.2019 18:10
Give heat transfer applications for the following, (i) gas turbines (propulsion) ) gas turbines (power generation). (iii) steam turbines. (iv) combined heat and power (chp). (v) automotive engines
Answers: 1
question
Engineering, 04.07.2019 18:10
Water in a partially filled large tank is to be supplied to the roof top, which is 8 m above the water level in the tank, through a 2.2-cm-internal-diameter pipe by maintaining a constant air pressure of 300 kpa (gage) in the tank. if the head loss in the piping is 2 m of water, determine the discharge rate of the supply of water to the roof top in liters per second.
Answers: 3
question
Engineering, 04.07.2019 18:10
You are making beer. the first step is filling the glass carboy with the liquid wort. the internal diameter of the carboy is 15 in., and you wish to fill it up to a depth of 2 ft. if your wort is drawn from the kettle using a siphon process that flows at 3 gpm, how long will it take to fill?
Answers: 1
question
Engineering, 04.07.2019 18:10
True or false (explain) (110)[111] is a slip system in bcc metals . the {111} family in fcc contains 8 planes. resolved shear stress (rss) in single crystals is just related to the applied stress. critical resolved shear stress (crss) in single crystal metals is direct proportional to the number of defects in the structure
Answers: 2
You know the right answer?
In a standard 6-day period, the production department programme a specific machine to work for 250 h...
Questions
question
Mathematics, 26.10.2020 02:20
question
Mathematics, 26.10.2020 02:20
question
Social Studies, 26.10.2020 02:20
question
History, 26.10.2020 02:20