Engineering, 19.02.2021 03:00 weeman7760

There are three 15 LCY trucks that will be used to transport the excavated soil. It takes 25 min for a truck to drive to the unloading site, unload and drive back to the excavation area. Instead of being idle till the trucks return from each truck cycle, the excavator unloads soil in a spoil bank at the same swing angle (90o). Calculate the volume of soil in the spoil bank at the end of the excavation. Total volume of excavation is 15,000 BCY.

ansver
Answers: 2

Another question on Engineering

question
Engineering, 04.07.2019 18:10
Calculate the bore of a cylinder that has a stroke of 18 inches and an extension time of 6 seconds at a flow rate of 4 gal/min.
Answers: 3
question
Engineering, 04.07.2019 18:10
What are the two (02) benefits, which may result from a successful implementation of preventive maintenance (pm) program in an organization? (clo3)a)- lean manufacturing b)-overlapping responsibilities c)-the planner is not qualified d)-accurate contractor information e)-reduction in equipment redundancies f)-accurate stores information
Answers: 3
question
Engineering, 04.07.2019 18:20
Have a greater impact on maintenance productivity than any other support group. (clo5) a)-the top management b)-inventory and purchasing c)-sub-contracting d)-cmms
Answers: 2
question
Engineering, 04.07.2019 19:10
What is the main objective of using reheat rankine cycle?
Answers: 3
You know the right answer?
There are three 15 LCY trucks that will be used to transport the excavated soil. It takes 25 min for...
Questions
question
English, 16.12.2020 01:20
question
Chemistry, 16.12.2020 01:20
question
English, 16.12.2020 01:20
question
Mathematics, 16.12.2020 01:20
question
Mathematics, 16.12.2020 01:20
question
Mathematics, 16.12.2020 01:20