What is the critical path and time duration?
A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C. B is an immediate predecessor of C. The activity durations are A=4, B=3, C=8.
(A) The critical path is A-B-C, duration 15.
(B) The critical path is A-C, duration 12.
(C) The critical path is A-B-C, duration 13.5
(D) The critical path cannot be determined withoutknowing PERT expected activity times.
(E) The network has no critical path.

ansver
Answers: 1

Another question on Engineering

question
Engineering, 04.07.2019 18:10
During a steady flow process, the change of energy with respect to time is zero. a)- true b)- false
Answers: 2
question
Engineering, 04.07.2019 18:10
Afluid flows with a velocity field given by v=(x/t)i.. determine the local and convective accelerations when x=3 and t=1.
Answers: 2
question
Engineering, 04.07.2019 18:20
Steam enters a converging nozzle at 3.0 mpa and 500°c with a at 1.8 mpa. for a nozzle exit area of 32 cm2, determine the exit velocity, mass flow rate, and exit mach number if the nozzle: negligible velocity, and it exits (a) is isentropic (b) has an efficiency of 94 percent
Answers: 2
question
Engineering, 04.07.2019 18:20
Ahe-xe mixture containing a 0.75 mole fraction of helium is used for cooling electronics in an avionics application. at a temperature of 300 k and atmospheric pressure, calculate the mass fraction of helium and the mass density, molar concentration and molecular weight of the mixture. if the cooling capacity is 10 l, what is the mass of the coolant?
Answers: 3
You know the right answer?
What is the critical path and time duration?
A simple CPM network has three activities, A, B,...
Questions
question
Chemistry, 15.10.2020 01:01
question
Mathematics, 15.10.2020 01:01
question
Social Studies, 15.10.2020 01:01