The contractor was awarded a contract to construct a parking lot for a small shopping center. the contractor plans to use single pusher scraper for site grading with a chain loading method.

it has been decided there will be total 11 scrapers, and for each scraper the estimated cycle time is 7 mins.

a) how many pushers are required to serve a fleet of 11 scrapers. b) the expected production of the scraper fleet if only 1 pusher is available. (production of a single scraper assuming adequate pusher support is 317 bcy/hr.

ansver
Answers: 1

Another question on Engineering

question
Engineering, 04.07.2019 18:10
Aflywheel accelerates for 5 seconds at 2 rad/s2 from a speed of 20 rpm. determine the total number of revolutions of the flywheel during the period of its acceleration. a.5.65 b.8.43 c. 723 d.6.86
Answers: 2
question
Engineering, 04.07.2019 18:10
Slip occurs via two partial dislocations because of (a) the shorter path of the partial dislocation lines; (b) the lower energy state through partial dislocations; (c) the charge balance.
Answers: 1
question
Engineering, 04.07.2019 18:20
Inspection for bearing condition will include: (clo4) a)-color b)-smell c)-size d)-none of the above
Answers: 1
question
Engineering, 04.07.2019 18:20
Asimple rankine cycle uses water as the working fluid. the water enters the turbine at 10 mpa and 480c while the condenser operates at 6 kpa. if the turbine has an isentropic efficiency of 80 percent while the pump has an isentropic efficiency of 70 percent determine the thermal efficiency