A3/8-in × 2-in aisi 1018 cold-drawn steel bar is cantilevered to support a static load of 550 lbf as illustrated. the bar is secured to the support using two 3/8 in-16 unc sae grade 4 bolts. assume the bolt threads do not extend into the joint. find the factor of safety for the following modes of failure: shear of the bolt, bearing on the bolt, bearing on the member, and bending of the member. give the overall joint factor of safety.

ansver
Answers: 2

Another question on Engineering

question
Engineering, 04.07.2019 18:10
Coiled springs ought to be very strong and stiff. si3n4 is a strong, stiff material. would you select this material for a spring? explain.
Answers: 2
question
Engineering, 04.07.2019 18:10
Different types of steels contain different elements that alter the characteristics of the steel. for each of the following elements, explain what the element does when alloyed with steel.
Answers: 2
question
Engineering, 04.07.2019 18:10
Ifa component is made of two or more materials with different modulus of elasticity (e), it is called a composite member and we calculate the factor·n". mention the formula for calculating n". also, ifn> 1, explain what will happen to the 1. transformed.gi) ifn 1, what will happen to the material when transformed material when
Answers: 1
question
Engineering, 04.07.2019 18:20
A3-mm-thick panel of aluminum alloy (k 177 w/m-k, c 875 j/kg-k and ? = 2770 kg/m) is finished on both sides with an epoxy coating that must be cured at or above t,-150°c for at least 5 min. the production line for the curing operation involves two steps: (1) heating in a large oven with air at ts,0-175°c and a convection coefficient of h, 40 w/m2. k, and (2) cooling in a large chamber with air at 25°c and a con- vection coefficient of he 10 w/m2.k. the heating portion of the process is conducted over a time interval te which exceeds the ime required to reach 150°c by 5 min (h = r + 300 s). the coating has an emissivity of ? = 0.8, and the temperatures of the oven and chamber walls are 175 and 25°c, respectively. if the panel is placed in the oven at an initial temperature of 25°c and removed from the chamber at a safe-to-touch tempera ture of 37°c, what is the total elapsed time for the two-step curing operation?
Answers: 3
You know the right answer?
A3/8-in × 2-in aisi 1018 cold-drawn steel bar is cantilevered to support a static load of 550 lbf as...
Questions
question
English, 21.10.2020 17:01
question
Mathematics, 21.10.2020 17:01