A software Company has just won a contract worth GH¢80m, if it delivers a successful product on time, but only GH¢40m, if this is late. It

faces a problem of whether to produce the work in-house or to

subcontract.

To subcontract the work would cost GH¢20m but based on past

experience would have only a 90% chance of being successful. In the

event of the software not being successful, there would be insufficient

time to re-write the whole package internally but there would still be the

options of either a late-rejection of the contract (at a further cost of

GH¢10m) or a late subcontracting of the work on the same terms as

before. With this late start, the local subcontractor is estimated to have

only a 50 / 50 chance of producing it late. In this case, the subcontractor

still has to be paid GH¢50m, regardless of whether he meets the

ansver
Answers: 1

Another question on Computers and Technology

question
Computers and Technology, 23.06.2019 11:30
Me dangers of social media and the internetexplain what each means: 1) social media and phones have become an addiction.2) outside people have access to you all the time.3) cyberstalking4) cyberbullying5) catphishing6) viruses7) identity theft8) credit card fraud9) hacking10) money schemes
Answers: 1
question
Computers and Technology, 24.06.2019 11:00
In three to five sentences, describe how you can organize written information logically and sequentially
Answers: 1
question
Computers and Technology, 24.06.2019 22:00
Need getting google account back, big issue
Answers: 2
question
Computers and Technology, 24.06.2019 23:30
Does anyone have the problem where you try to watch a video to get your answer but it brings up a thing asking your gender to make ads relevant but it doesn't load? btw i won't be able to see the answer so use the comments .
Answers: 1
You know the right answer?
A software Company has just won a contract worth GH¢80m, if it delivers a successful product on ti...
Questions
question
Mathematics, 20.11.2020 17:10