You have a project with the following tasks: Task A takes 40 hours and can start after the project starts. Task B takes 25 hours and should happen after the project starts. Task C must happen after Task A and takes 35 hours. Task D must happen after Tasks B and C and takes 30 hours. Task E must take place after Task C and takes 10 hours. Task F takes place after Task E and takes 22 hours. a. Draw the network diagram
b. What is the critical path and what is the length of the critical path?
c. If Task B actually takes 37 hours, what is the effect on the project?
d. What tasks must be completed before task D can begin?
e. If senior management tells you to complete the project 20 hours early, what is the project float? How can you meet this requirement? Does the critical path change?

ansver
Answers: 3

Another question on Computers and Technology

question
Computers and Technology, 23.06.2019 08:00
The managing director of a company sends a christmas greeting to all his employees through the company email. which type of network does he use? he uses an .
Answers: 3
question
Computers and Technology, 24.06.2019 00:20
The guy wire bd exerts on the telephone pole ac a force p directed along bd. knowing the p must have a 720-n component perpendicular to the pole ac, determine the magnitude of force p and its component along line ac.
Answers: 2
question
Computers and Technology, 24.06.2019 18:30
Is a type of bullying that takes place when a person intentionally posts negative information about another that is not true
Answers: 1
question
Computers and Technology, 25.06.2019 00:00
What function key is used to enable the spelling and grammar function
Answers: 1
You know the right answer?
You have a project with the following tasks: Task A takes 40 hours and can start after the project s...
Questions
question
English, 20.08.2019 14:50
question
Mathematics, 20.08.2019 14:50